Executive Summary
On February 19, 2026, FERC approved one of the most consequential regulatory packages in the history of inverter-based resource (IBR) oversight in the United States. The RD26-1/2/3 docket bundle encompasses five new or revised NERC reliability standards — including the landmark MOD-026-2, updates to MOD-032, MOD-033, IRO-010, and TOP-003 — along with three new defined terms added to the NERC Glossary. Taken together, these standards establish enforceable, concrete requirements for IBR data sharing and dynamic model validation across the bulk electric system.
The timing is not incidental. IBRs — primarily utility-scale wind, solar photovoltaic, and battery energy storage systems — now constitute a material and growing share of generation capacity on most U.S. transmission systems. Their electromagnetic behavior during grid disturbances differs fundamentally from that of synchronous generators, and the models used by transmission planners and reliability coordinators to simulate that behavior have, in many documented cases, been dangerously inaccurate. The RD26-1/2/3 package is FERC and NERC's most direct regulatory response to that modeling gap to date.
This memo provides a detailed analysis of what the RD26-1/2/3 package contains, why it matters, and what it demands from Generator Owners, Generator Operators, Transmission Planners, and Reliability Coordinators. It also examines the technical burden introduced by the new electromagnetic transient (EMT) cross-validation requirement embedded in MOD-026-2, assesses the market and operational implications for IBR developers and asset managers, and offers forward-looking analysis of where IBR compliance policy is likely to go over the next 24 to 36 months.
1. Introduction
The integration of inverter-based resources into the North American bulk electric system has outpaced the regulatory frameworks designed to govern their behavior. For most of the past decade, NERC and FERC have been engaged in a sustained effort to close the gap between the operational realities of a high-IBR grid and the compliance standards originally written for synchronous generation. The RD26-1/2/3 approval on February 19, 2026 represents the most comprehensive single-day advancement of that effort to date.
The three docket numbers — RD26-1, RD26-2, and RD26-3 — correspond to distinct but interrelated NERC petitions addressing two foundational reliability problems: first, the inadequacy of data sharing practices between Generator Owners and the entities responsible for planning and operating the transmission system; and second, the persistent inaccuracy of the dynamic models used to simulate IBR behavior in power flow and stability studies.
These are not abstract concerns. NERC's 2023 and 2024 State of Reliability reports documented multiple instances in which IBR fleets tripped offline during grid disturbances in ways that neither operators nor planners had anticipated — in part because the models in use did not reflect actual inverter control settings, firmware versions, or plant-level protection configurations. The February 19 order translates years of NERC event analysis and standards development activity into binding, enforceable obligations.
This memo is written for energy industry executives, regulatory professionals, and technical leaders who need to understand not just what the standards say, but what they require in practice, what they will cost, and what they signal about the direction of IBR compliance policy going forward.
2. Background: The IBR Modeling Problem
2.1 Why IBR Models Fail
Synchronous generators — gas turbines, steam turbines, hydro units — have well-understood electromechanical characteristics that have been modeled with reasonable accuracy for decades. Their response to voltage and frequency disturbances is governed by physical inertia and rotor dynamics that are relatively predictable and stable across operating conditions.
IBRs operate through power electronics. Their behavior during grid disturbances is governed almost entirely by software: inverter control algorithms, protection relay settings, and plant-level control logic. This means that two physically identical wind turbines from the same manufacturer can behave very differently during a low-voltage event if their firmware versions or control parameter settings differ. It also means that a model validated at commissioning may become inaccurate after a firmware update — a routine occurrence that has historically gone undocumented in the models used by transmission planners.
NERC's 2022 report on the August 16, 2021 Southwest disturbance event — in which approximately 900 MW of solar generation tripped offline in rapid succession during a transmission fault in California — identified model inaccuracy as a central contributing factor. Planners had not anticipated the scale of the trip because the positive-sequence models in use did not accurately represent the low-voltage ride-through settings of the affected units. This was not an isolated incident; similar findings appeared in NERC's analysis of the May 9, 2021 ERCOT disturbance and several subsequent events.
2.2 The Pre-RD26 Regulatory Landscape
Prior to the RD26-1/2/3 package, the primary standards governing IBR model validation were MOD-026-1 and MOD-027-1. MOD-026-1 addressed verification of generator voltage regulator models, while MOD-027-1 addressed turbine/governor and load control models. These standards were designed primarily with synchronous generators in mind and applied to IBRs only by extension. The split between voltage/reactive and frequency/active control domains created administrative and technical confusion for Generator Owners managing IBR fleets, since the control systems of a modern inverter do not neatly separate along those lines.
IRO-010 and TOP-003 established data exchange requirements between Generator Owners and reliability coordinators or transmission operators, but these requirements were not specifically calibrated to the data types most critical for IBR modeling — particularly electromagnetic transient (EMT) model packages, control block diagrams, and plant-level protection settings.
The result was a compliance environment in which Generator Owners could be technically in compliance with existing standards while still providing models that were materially inaccurate, incomplete, or outdated.
2.3 NERC's Standards Development Process Leading to RD26
NERC's Project 2023-03 (IBR Model Validation) and related standards development activities produced the draft standards that FERC ultimately approved on February 19, 2026. The development process involved extensive stakeholder engagement, including multiple rounds of industry comment and ballot, and reflected significant input from transmission planners, reliability coordinators, and IBR manufacturers. The three-docket structure of the FERC approval — RD26-1 addressing data sharing updates to IRO-010 and TOP-003, RD26-2 addressing MOD-032 and MOD-033 updates, and RD26-3 addressing the new MOD-026-2 standard — reflects the distinct but interrelated nature of the underlying reliability problems being addressed.
3. What the RD26-1/2/3 Package Contains
3.1 MOD-026-2: Unified Dynamic Model Verification
MOD-026-2 is the centerpiece of the RD26-1/2/3 package and the standard with the most significant technical and operational implications for Generator Owners. It consolidates and replaces both MOD-026-1 and MOD-027-1, eliminating the artificial separation between voltage/reactive power control verification and frequency/active power control verification. For IBRs, this consolidation reflects the physical reality that a single inverter control system governs both domains simultaneously.
The most consequential new requirement in MOD-026-2 is the mandate for cross-validation between electromagnetic transient (EMT) models and positive-sequence (phasor-domain) models. Under the prior standards, Generator Owners were generally required to provide positive-sequence models validated against field measurement data. EMT models — which simulate the high-frequency switching dynamics of inverter hardware and are computationally far more demanding — were not explicitly required for most facilities.
Under MOD-026-2, facilities not identified by their Transmission Planner as requiring full EMT models must still provide an integrated plant model that includes unit-level test data — either factory acceptance testing or hardware-in-the-loop (HIL) testing for large-signal disturbances — and must demonstrate cross-validation between their EMT and positive-sequence model responses. This is a significant new requirement. It means that Generator Owners must either develop and maintain EMT models in-house or retain qualified third-party modeling engineers capable of doing so. For large IBR fleets with multiple inverter types across multiple manufacturers, this represents a substantial and recurring technical cost.
The standard also introduces new requirements around model documentation, including version control for control parameter settings and a defined process for updating models following firmware changes or significant plant modifications. This addresses one of the most persistent sources of model inaccuracy identified in NERC's post-event analyses.
3.2 MOD-032 and MOD-033 Updates (RD26-2)
MOD-032 governs data requirements for steady-state and dynamic modeling, establishing what data Generator Owners must provide to Transmission Planners for use in planning studies. The RD26-2 updates to MOD-032 expand the required data set for IBRs to include plant-level protection settings, reactive power capability curves as a function of active power output, and control system block diagrams at a level of detail sufficient to support EMT model development. These requirements operationalize the data sharing objectives of the broader RD26 package by specifying exactly what information must flow from Generator Owners to the entities responsible for system modeling.
MOD-033 addresses model validation from the perspective of Transmission Planners, establishing requirements for how planners must validate the models they receive from Generator Owners and how they must document and communicate validation results. The RD26-2 updates to MOD-033 introduce new requirements for planners to flag and escalate model discrepancies — cases where simulation results diverge materially from observed field behavior — and to track the resolution of those discrepancies through a defined process. This creates a feedback loop between field observations and model accuracy that was largely absent from the prior standards framework.
3.3 IRO-010 and TOP-003 Updates (RD26-1)
IRO-010 governs the data sharing obligations of Generator Owners toward Reliability Coordinators, while TOP-003 governs data sharing toward Transmission Operators. The RD26-1 updates to both standards expand the scope of required data to include IBR-specific information not previously enumerated: EMT model packages, hardware-in-the-loop test reports, and real-time telemetry data sufficient to support post-disturbance analysis.
Critically, the updated standards establish defined timelines for data delivery. Generator Owners must provide updated model packages within a specified number of days following a firmware update, a significant plant modification, or a request from a Reliability Coordinator or Transmission Operator. This time-bound obligation is new and represents a meaningful compliance risk for Generator Owners who do not have systematic processes for tracking and documenting plant changes.
3.4 New NERC Glossary Definitions
The three new defined terms added to the NERC Glossary as part of the RD26 package — while less visible than the standards themselves — are significant because definitional clarity is a prerequisite for consistent enforcement. The new definitions address terms central to the IBR modeling context, including the distinction between unit-level and plant-level models and the specific technical meaning of "cross-validation" as used in MOD-026-2. Precise definitions reduce the interpretive ambiguity that has historically allowed significant variation in how Generator Owners have approached model validation obligations.
4. Technical Implications
4.1 The EMT Cross-Validation Requirement: A Closer Look
The requirement for cross-validation between EMT and positive-sequence models deserves detailed examination because it is both technically complex and likely to be the most costly compliance element of the RD26 package for most Generator Owners.
EMT simulation tools — such as PSCAD, EMTP-RV, and similar platforms — simulate the behavior of power electronic devices at sub-cycle timescales, capturing the switching dynamics of inverter hardware that are invisible to positive-sequence (phasor-domain) tools like PSS/E or PowerWorld. EMT models are computationally intensive and require specialized expertise to develop, parameterize, and validate. Historically, EMT modeling has been primarily the domain of transmission planners and interconnection studies engineers; Generator Owners have generally not been required to develop or maintain EMT models as part of their compliance obligations.
MOD-026-2 changes this by requiring that Generator Owners demonstrate that their positive-sequence models produce results consistent with their EMT models under defined test conditions. This cross-validation requirement has several practical implications. First, it means that Generator Owners must either develop EMT models themselves or obtain them from inverter manufacturers — a process that is not always straightforward, as some manufacturers treat detailed control block diagrams as proprietary information. Second, it means that Generator Owners must be able to run and interpret EMT simulations, or retain engineers who can. Third, it creates an ongoing maintenance obligation: as inverter firmware evolves, both the EMT and positive-sequence models must be updated and re-cross-validated.
For Generator Owners with large, diverse IBR fleets — particularly those with multiple inverter manufacturers and models — this is a substantial technical undertaking. The cost burden is not evenly distributed; smaller operators and independent power producers with limited internal engineering resources will face proportionally higher costs than large integrated utilities with in-house modeling teams.
4.2 Hardware-in-the-Loop Testing Requirements
The reference to hardware-in-the-loop (HIL) testing in MOD-026-2 introduces another new technical dimension. HIL testing involves connecting a physical inverter controller to a real-time digital simulator, allowing large-signal disturbance responses to be tested under controlled laboratory conditions that would be impractical or unsafe to replicate in the field. HIL test results are increasingly accepted by NERC and transmission planners as a substitute for field measurement data in cases where field testing is not feasible — for example, for large-signal disturbances that would require deliberately inducing fault conditions on an operating grid.
The requirement that integrated plant models include components representing unit-level HIL testing for large-signal disturbances means that Generator Owners must either conduct HIL testing themselves, arrange for manufacturers to conduct it on their behalf, or obtain and document manufacturer-provided HIL test results. This is a new obligation with no direct precedent in the prior MOD-026-1/MOD-027-1 framework.
4.3 Implications for Positive-Sequence Model Accuracy
One of the underlying motivations for the EMT cross-validation requirement is the well-documented tendency of positive-sequence models to overestimate IBR ride-through performance under certain disturbance conditions. When a positive-sequence model predicts that an IBR will remain connected through a voltage disturbance, but the actual inverter — and the EMT model that accurately represents it — would trip, the positive-sequence model is providing false assurance to planners and operators. The cross-validation requirement is designed to surface these discrepancies systematically rather than allowing them to persist undetected until a real disturbance reveals them.
This has implications not just for compliance but for the quality of transmission planning studies more broadly. If the cross-validation process reveals systematic discrepancies between positive-sequence and EMT models across a significant portion of the IBR fleet, it will require a reassessment of the reliability margins embedded in existing planning studies — a potentially significant undertaking for regional transmission organizations and transmission planners.
5. Regulatory Analysis
5.1 FERC's Jurisdictional Authority and Enforcement Posture
FERC's approval of the RD26-1/2/3 package under Section 215 of the Federal Power Act makes the five new and revised standards mandatory and enforceable for all registered entities subject to NERC's compliance monitoring and enforcement program. Violations are subject to civil penalties of up to $1.496 million per violation per day under FERC's current penalty guidelines, though actual penalties in reliability standard cases are typically determined through a fact-specific analysis of risk, culpability, and remediation.
The February 19 order is notable not just for what it approves but for the signal it sends about FERC's enforcement posture toward IBR compliance. FERC has been increasingly explicit in its public statements and orders about the reliability risks posed by inaccurate IBR models, and the RD26 package reflects a deliberate decision to move from guidance and encouragement to binding obligation. Generator Owners who have been in a "wait and see" posture regarding IBR model validation should treat the February 19 order as a clear signal that that posture is no longer sustainable.
5.2 Interaction with Order 901 and the PRC Standards
The RD26-1/2/3 package does not exist in isolation. It must be understood in the context of FERC's broader IBR compliance agenda, which includes Order 901 (approving PRC-029-1 and PRC-030-1, the IBR ride-through and disturbance monitoring standards), the ongoing implementation of NERC's IBR registration categories, and the Category 2 IBR registration deadline of May 15, 2026.
The interaction between the MOD standards (which address model accuracy) and the PRC standards (which address operational performance and disturbance monitoring) is particularly important. PRC-029-1 requires IBRs to remain connected during voltage and frequency disturbances and establishes performance requirements that must be demonstrated through field testing or simulation. The accuracy of those simulations depends directly on the quality of the models that MOD-026-2 is designed to improve. In other words, PRC-029-1 compliance is downstream of MOD-026-2 compliance: if your models are wrong, your PRC-029-1 simulations may be telling you you're compliant when you're not.
5.3 NERC's Category 2 IBR Registration and the Expanding Compliance Population
The May 15, 2026 Category 2 IBR registration deadline brings a new population of entities into the NERC compliance framework: owners and operators of non-BES inverter-based generating resources with aggregate nameplate capacity of 20 MVA or greater delivering to a common point of connection at 60 kV or above. Many of these entities have no prior experience with NERC compliance obligations and may be unaware that the RD26-1/2/3 standards will apply to them.
The combination of the Category 2 registration deadline and the RD26 approval creates a compressed compliance timeline for a significant number of IBR operators. Entities that register in May 2026 will immediately face model validation obligations under MOD-026-2 for which they may have no existing documentation, no established relationships with modeling engineers, and no internal compliance infrastructure. This is a systemic risk that NERC and the regional entities will need to manage carefully through their compliance monitoring programs.
6. Market and Operational Implications
6.1 Cost Burden Distribution Across the Industry
The RD26-1/2/3 package will impose significant new costs on the IBR development and operations community. The magnitude and distribution of those costs will depend on several factors: the size and diversity of an operator's IBR fleet, the availability of manufacturer-provided EMT models and HIL test data, the state of existing model documentation, and the operator's internal engineering capacity.
For large integrated utilities and independent power producers with established compliance programs and in-house engineering teams, the incremental cost of RD26 compliance is likely manageable — primarily a matter of expanding existing workflows to incorporate EMT cross-validation and enhanced data sharing. For smaller operators, community solar developers, and independent storage operators who are newly subject to NERC registration under the Category 2 framework, the cost burden could be proportionally significant. Industry observers have estimated that developing and validating a full EMT model package for a single IBR facility can cost between $50,000 and $200,000 depending on complexity, with ongoing maintenance costs of $20,000 to $50,000 per year per facility.
6.2 Inverter Manufacturer Obligations and Proprietary Model Concerns
One of the persistent tensions in IBR model validation has been the reluctance of inverter manufacturers to share detailed control block diagrams and parameter sets, which they regard as proprietary intellectual property. The RD26 package does not directly resolve this tension — it places the compliance obligation on Generator Owners, not manufacturers — but it intensifies the pressure on Generator Owners to obtain the information they need from their equipment suppliers.
This is likely to accelerate existing trends toward contractual requirements for model deliverables in IBR equipment procurement agreements. Generator Owners who have not already incorporated model documentation requirements into their equipment supply contracts will need to do so going forward. For existing facilities with legacy equipment contracts that do not include these provisions, negotiating access to EMT model packages and HIL test data from manufacturers may be difficult and costly.
6.3 Transmission Planning Study Quality and System Reliability
At the system level, the most significant long-term impact of the RD26-1/2/3 package may be an improvement in the quality of transmission planning studies and, by extension, in the reliability of the decisions those studies inform. If the cross-validation process reveals that positive-sequence models for a material fraction of the IBR fleet have been systematically overstating ride-through performance, the implications for system planning could be substantial. Reliability margins that appeared adequate under existing models may prove insufficient. Interconnection agreements and planning studies completed under the old standards may need to be revisited.
This is not a worst-case scenario — it is a likely consequence of applying more rigorous validation standards to a fleet of resources whose models have been known to be inaccurate. The transition will be disruptive in the near term but is essential to the long-term reliability of a grid that is increasingly dependent on IBR performance during disturbances.
7. Looking Ahead: Predictions and Forward-Looking Analysis
7.1 Enforcement Actions Will Follow
FERC and NERC have historically allowed a grace period between the effective date of new reliability standards and the initiation of enforcement actions, recognizing that compliance programs require time to develop. However, the RD26-1/2/3 package comes after years of documented IBR modeling failures and multiple high-profile disturbance events. It would be reasonable to expect that NERC's compliance monitoring program will begin active assessment of MOD-026-2 compliance within 12 to 18 months of the standard's effective date, with formal enforcement actions likely to follow for entities that have made no demonstrable progress toward compliance.
The Category 2 IBR registration population will be a particular focus of compliance monitoring, as newly registered entities are by definition starting from zero in terms of model documentation. Regional entities are likely to develop specific compliance monitoring protocols for this population.
7.2 EMT Modeling Will Become a Core Competency Requirement
The EMT cross-validation requirement in MOD-026-2 will, over time, make EMT modeling a baseline competency for IBR Generator Owners rather than a specialized capability reserved for large utilities and transmission planners. This will drive demand for EMT modeling engineers, expand the market for EMT simulation software licenses, and create pressure on inverter manufacturers to provide more complete and accessible model packages as a standard part of equipment delivery.
It will also accelerate the development of automated model validation tools — software platforms capable of running standardized cross-validation test cases and generating compliance documentation with reduced manual effort. Several engineering consulting firms and software developers are already investing in this space, and the RD26 package will significantly expand the addressable market for such tools.
7.3 FERC Will Continue to Expand the IBR Compliance Framework
The RD26-1/2/3 package is not the end of FERC's IBR compliance agenda — it is a milestone in an ongoing process. NERC has several active standards development projects addressing IBR-related reliability gaps that were not covered by the RD26 package, including projects addressing IBR protection coordination, reactive power capability verification, and the reliability implications of grid-forming inverter technology.
FERC's Order 901 (PRC-029-1/PRC-030-1) and the RD26 package together establish a comprehensive framework for IBR operational performance and model accuracy. The next phase of regulatory development is likely to address the reliability implications of very high IBR penetration scenarios — situations in which IBRs constitute the majority of online generation during certain operating conditions — and the adequacy of existing planning and operating standards for those scenarios.
7.4 The Grid-Forming Inverter Transition Will Create New Regulatory Challenges
Grid-forming inverter technology — which enables IBRs to provide synthetic inertia and voltage support in ways that more closely resemble synchronous generator behavior — is advancing rapidly and is already being deployed in some markets. The current RD26 framework is designed primarily for grid-following inverters. As grid-forming technology penetrates the market, it will create new modeling and validation challenges that the existing standards framework is not fully equipped to address. NERC and FERC will need to develop new standards or significantly revise existing ones to account for the distinct behavioral characteristics of grid-forming IBRs.
7.5 Regional Variation in Implementation Will Create Compliance Complexity
While NERC reliability standards are national in scope, their implementation is carried out by regional entities — SERC, ReliabilityFirst, WECC, MRO, and others — that have some latitude in how they conduct compliance monitoring and enforcement. There is likely to be meaningful regional variation in the pace and rigor of MOD-026-2 implementation, at least in the near term. Generator Owners with assets in multiple regions will need to monitor regional entity guidance and compliance bulletins closely, as the practical compliance requirements may differ across regions even under a uniform national standard.
8. Conclusion
The FERC RD26-1/2/3 approval of February 19, 2026 is a defining moment in the evolution of IBR compliance policy in the United States. By establishing enforceable requirements for EMT cross-validation, enhanced data sharing, and systematic model maintenance, the package addresses the most persistent and consequential reliability gap in the current IBR compliance framework: the gap between what models predict and what inverters actually do during grid disturbances.
The technical and operational demands of the new standards are substantial, and the cost burden will fall unevenly across the industry. Generator Owners who have invested in robust model documentation and validation programs will find the transition manageable. Those who have not — and there are many — face a compressed timeline for building capabilities that cannot be developed overnight. The May 15, 2026 Category 2 IBR registration deadline adds urgency for a newly expanded population of entities that may be encountering NERC compliance obligations for the first time.
The broader significance of the RD26 package lies in what it signals about the direction of grid reliability policy. FERC and NERC have concluded, based on years of disturbance data and event analysis, that the existing IBR compliance framework is inadequate for a grid in which inverter-based resources are increasingly central to reliable operation. The February 19 order is the clearest expression yet of their intent to change that.
Select Citations
- (FERC): February 19, 2026 Commission Meeting — Summaries of Actions Taken.
- (FERC): Order 909: Approval of PRC-029-1 and PRC-030-1 Inverter-Based Resource Reliability Standards.
- (NERC): MOD-026-2: Verification of Models and Data for Generator Excitation Control System or Plant Volt/VAr Control Functions.
- (NERC): State of Reliability 2024.
- (NERC): IBR Category 2 Registration Requirements — Implementation Guidance.
- (ReliabilityFirst): IBR Category 2 Registration Compliance Advisory.
- (NERC): August 16, 2021 Southwest Disturbance — Preliminary Report.
- (ENTRUST): MOD-026-2 Technical Summary and Compliance Implications.



